In the heart of Maharashtra’s infrastructure boom, Govardhani Constructions, led by Mr. Nilesh Mhatre, has emerged as a trusted name in the supply of premium-grade aggregates for roads, RMC plants, and urban development projects in and around Mumbai. As demand surged and specifications tightened, Mr. Mhatre recognized the need to scale operations—first with a reliable two-stage setup, and later with a full-fledged three-stage plant that would offer superior shaping and consistency. Both times, he chose Taurian MPS.

The Journey: From 2-Stage to 3-Stage Crushing

Phase 1: Laying the Foundation with a Two-Stage Plant

In 2017, Govardhani Constructions partnered with Taurian to install a 2-stage crusher plant, powered by a Taurian TJ300 Primary Jaw Crusher and CG250 Secondary Cone Crusher. This configuration was perfect for producing coarse aggregates for road base and structural backfill, handling basalt and laterite with ease.

Key outcomes:

  • Increased plant output by 30%

  • Reduced boulder handling issues

  • Established reliable aggregate supply for municipal tenders

Phase 2: Upgrading to a 3-Stage Setup with VSI

By 2021, with stricter demands from infrastructure clients and a growing footprint in plaster sand and concrete sand supply, Mr. Mhatre made a strategic decision: invest in a 3-stage crushing solution with advanced shaping capability.

Taurian added the T300 Vertical Shaft Impact Crusher (VSI) to the existing setup, transforming the plant into a high-performance unit capable of delivering well-graded, cubical M-sand and 10–20 mm concrete aggregates.

Belapur 3

The Challenge

Operating near urban zones in Mumbai, Govardhani Constructions needed a setup that balanced production efficiency, environmental compliance, and low downtime. Terrain variations, inconsistent raw material sizes, and noise control were all key considerations. Additionally, upgrading from a two-stage to a three-stage plant without disrupting existing operations required precise planning and seamless execution.

Belapur 2

Results & Impact

Since the addition of the VSI third stage, Govardhani Constructions has:

  • Achieved 35% higher yield of sellable products

  • Reduced fines generation and reprocessing needs

  • Expanded market reach with premium-quality plaster and concrete sand

  • Lowered maintenance costs through modular equipment design and quick liner change features

In Govardhani Constructions’ field engineer’s words:

“We trusted Taurian once, and it paid off. When we needed to upgrade, there was no doubt. Their support, quality, and performance are unmatched.”

pile of gravel

At Taurian, we take pride in being growth partners for our customers. The journey with Govardhani Constructions—from a 2-stage setup to a high-efficiency 3-stage plant—is a testament to our commitment to modular solutions, customer-first engineering, and long-term service support. We continue to support their expansion goals as they deliver the building blocks of Mumbai’s next chapter in infrastructure development.